Kings Road arches redevelopment for Brighton and Hove Council  

Brighton and Hove City Council (BHCC) appointed Project Centre to develop the Phase 4 design of the seafront redevelopment at Kings Roach Arches. The tenanted structure houses numerous businesses and supports the Upper Promenade A259 footway and Grade II listed pedestrian barriers. The arches are deteriorating and have a limited load capacity. The goal is to improve the load-carrying capacity of the structure whilst retaining its historic character and enhancing the interior tenanted spaces.  

BHCC is a Unitary Authority and Highway Authority for its non-trunk roads. They have a duty to maintain public roads and ensure they are safe for normal traffic. The roof slabs of the existing arch-fronted structure are incapable of supporting normal traffic accidental vehicle loads and require strengthening. The upper promenade is heavily used by pedestrians and cyclists and is immediately adjacent to the A259 Kings Road, the primary east-west route through Brighton. The structure accommodates shops, cafes, and stores whose operations would be majorly disrupted by any refurbishment works. 

Project Centre’s scope included the structural, highway, public realm, architectural, mechanical & electrical (M&E) RIBA stage 3 and 4 design for the refurbishment. This includes obtaining planning approval, building control approval, listed building consent, and highway structure technical approval. 

Engaging stakeholders

The broad scope and multiple stakeholder interfaces presented several project risks. Project Centre engaged with BHCC and other key stakeholders to determine the main scheme objectives including aesthetics, maximising marketable retail space, and reducing impacts to businesses and the public.  

Using this, Project Centre developed a detailed project execution plan to establish a consistent delivery process and stakeholder engagement approach to mitigate the identified project risks. This included the appointment of architectural and M&E supply chain partners and a clear definition of responsibilities between all organisations. 

Investigating site data

Project Centre identified the need for various site investigations to inform the design. In collaboration with the client and stakeholders, we scoped, planned, and carried out the site investigations to optimise the data collected while minimising disruptions to business operations. 

The design phase

Project Centre’s structural design features an integral reinforced concrete frame on piled foundations, built around the retained rear wall of the structure. Close coordination with our design partners was essential to restore the brick façade and maintain the current appearance whilst creating a serviced, flexible open internal space that complies with modern building standards.  

Project Centre also specified arch infilling and repairs to smaller arches at the east of the scheme and modifications to a private steel footbridge. Project Centre deliverables include a fully detailed design package, Site Information and Works Information for construction.

We also fulfilled the Principal Designer role under the CDM regulations to coordinate health and safety in the pre-construction phase and undertake design risk identification and mitigation. A clear understanding of buildability constraints and operational requirements was key to developing a safe design. 

Project Centre considered environmental, social, and economic factors throughout this project in the design approach and selection of a sustainable, durable, and maintainable solution. We were also responsible for developing a build sequence that minimised disruption while considering site logistics and public user group requirements at all construction stages. This included determining suitable site extents and developing temporary diversion routes for cyclists and pedestrians. 

In addition to delivering the design, Project Centre supported BHCC with developing a business case to secure funding for the construction stage.  

Project Centre’s collaborative approach with the client, stakeholders, and supply chain has been key to the successful delivery of a high-quality design solution that exceeds the project requirements. Our proactive approach towards risk management has ensured the successful delivery and resilience of the project.  

Through applying our design expertise, effective project management, and supply chain coordination, we produced a sustainable, safe, buildable design whilst mitigating project risk and disruption. 

Project Centre’s technical and managerial abilities have been essential in delivering this complex multidisciplinary scheme and assisting Brighton & Hove with coordinating multiple stakeholders and requirements to successfully meet the project brief.

Brighton and Hove Council

Speak to the team: Enquiries – Marston Holdings

Translate »

Make a payment

Other ways to pay Marston:

0333 320 1100

Marston - 24-hour automated payment line

0333 320 1822

Speak to Marston team to make a payment or to discuss your circumstances

Engage logo

For payments to Engage Services:

0333 3206 200

Speak to Engage Services team to make a payment

Customer support

Speak to Marston team to make a payment or discuss your circumstances:

0333 320 1822

Our opening hours are 8 AM to 8 PM Monday to Friday, 8 AM to 4 PM on Saturdays.

Contact by post:

It is always quicker and easier to contact us by phone or email. If you do need to send us anything in the post, please send it to:

Marston, PO Box 324,
Rossendale, BB4 0GE

To pay by post, send a postal order, cheque or banker’s draft, made payable to ‘Marston’ to the address above. Make sure that you write your name and our reference number on anything you send us and if sending us a payment, on the back of the postal order, cheque or banker’s draft so we know what the payment is for.

If you are an Engage Services customer,

click here for help,

or to speak to one of our team, call

0333 320 6200

.

If you have received a Penalty Charge Notice (PCN) you must follow the instructions on the reverse of the notice which contains full contact details for the applicable enforcing authority.

Transfer Up instruction form

This service allows you to apply for County Court Judgments to be transferred to the High Court for enforcement.

Writ of delivery instruction form

Our Enforcement Officers are well equipped and experienced in recovering all types of fixed assets whether it be a single car or fleet.

Money judgment enforcement form

We can enforce judgments obtained in the High Court and almost any judgment issued in the County Court.

Commercial forfeiture instruction form

Landlords may instruct us to take peaceful possession of their commercial property.

CRAR enforcement form

Instruct us to recover commercial rent arrears.

Trespasser removal enforcement form

We can handle the process quickly and resolutely. Our dedicated team will attend the scene on receipt of the warrant and effect eviction without delay.

Residential possession enforcement form

Instruct us for evicting residential tenants.

Process serving and tracing instruction form

We specialise in process serving throughout England and Wales. Court and legal documents are served on a same day-basis when required. We also undertake trace enquiries.

Employment Tribunal Enforcement Form

Instruct us to enforce employment tribunal awards. We can apply to the court to register the award as a Judgment.

European Enforcement Order Instruction Form

If you have a Judgment from a Country outside of the Jurisdiction of England and Wales but where the Debtor resides in England and Wales then we can assist you.

New business enquiry - Marston Holdings

Get in touch with our specialist team

New business enquiry - ParkTrade

Get in touch with our specialist team

New business enquiry - Engage

Get in touch with our specialist team

New business enquiry - NSL

Get in touch with our specialist team

New business enquiry - Videalert

Get in touch with our specialist team

Contact us

Debt recovery and enforcement services

Client support

Scott and Co logo

For more information

Scott & Co (Scotland) LLP

9 Melville Crescent Edinburgh, EH3 7LZ

0333 3206 871

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

ParkTrade logo

For more information

ParkTrade Europe AB

Sturegatan 16, 114 36 Stockholm, Sweden

+46 8 663 54 00

Business enquiries

+44 333 3202 985

Media enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Marston Holdings Logo

For more information

Marston Holdings

Rutland House, 8th Floor, 148 Edmund street, Birmingham, B3 2JR.

0333 3203 355

Business enquiries

0333 3202 985

Media enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Marston Holdings Logo

For more information

Marston High Court

5th Floor, 148 Great Charles Street, Queensway, Birmingham, B3 3HT

0333 3202 549

Business enquiries

Contact by post:

5th Floor, 148 Great Charles Street, Queensway
Birmingham, B3 3HT
DX 13014 Birmingham.

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Engage logo

For more information

Engage

Wavell House, Holcombe Road, Rossendale BB4 4NB

0333 320 6200

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

NSL logo

For more information

NSL Limited

12th Floor, One America Square, London, EC3N 2LS

If you have received a Penalty Charge Notice (PCN) you must follow the instructions on the reverse of the notice which contains full contact details for the applicable enforcing authority.

0333 3203 355

Business enquiries

NSL checking - Identity Verification Service

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Videalert logo

For more information

Videalert Limited

The Clock House, 87 Paines Lane, Pinner, Middlesex, HA5 3BY

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.

Client support

Project Centre logo

For more information

Project Centre Limited

0330 1358 950

Business enquiries

Business enquiries form

Use our online form and a member of our team will be in touch as soon as possible.